Archi Isani Block E is a 29-storey building of the Isani complex, which is located 2 minutes' walk from the metro station "Isani", on Navtlughi street, next to the "Carrefour" hypermarket. The complex covers 10,000 sq.m. green yard with children's and sports fields. Environmentally friendly, energy-efficient building block of the German brand YTONG is used in the construction, which maintains the temperature and saves energy by 40%, which reduces utility bills. The facade is covered with the highest quality Alucobond material.
Square
Children's playground
Stadium
Parking
Generator
Water Reservoir
Square
Children's playground
Stadium
Parking
Generator
Water Reservoir
The 27th floor screed work has been completed;
The installation of apartment doors from the 3rd to the 5th floor has been completed;
The installation of apartment doors from the 25th to the 27th floor is in progress;
Facade plastering work on the balconies from the 10th to the 16th floor is being completed;
Installation of metal railings on balconies from the 3rd to the 29th floor is being completed;
Ceramogranite laying work on balconies from the 10th to the 16th floor is being completed;
Ceramogranite laying work on balconies from the 20th to the 22nd floor is being completed;
Drinking water reservoir insulation work is being completed;
Installation of fire air ducts in the corridors of the 3rd to 29th floors is being completed;
Installation of apartment doors on the 8th floor is being completed;
Ventilated facade installation work is in progress;
Passenger elevator installation is being completed;
28th and 29th floor screed work is in progress;
Installation of screeds from the 18th to the 27th floor is in progress;
Ceramogranite laying work on balconies from the 4th to the 7th floor is in progress;
Ceramogranite laying work on balconies on the 18th and 19th floors is in progress;
Ceramogranite laying work on balconies from the 23rd to the 27th floor is in progress;
Ceramogranite laying work in common areas from the 23rd to the 27th floor is in progress;
Installation of apartment doors on the 6th and 7th floors is in progress;
Installation of apartment doors on the 24th floor is in progress;
Installation of screeds on the 25th and 26th floors is in progress;
Painting work of common areas from the 3rd to the 12th floor is in progress;
Ytong Block
Heidelberg Concrete
Low emission glass
HPL Panels
HPL Panels
HPL Panels
Caparol Paint
Archi Isani
10, Navtlughi Str., Tbilisi
Ongoing
Choose area type
Choose floor
Choose area
Number of rooms
Apartment price
Archi Isani
Block E | Apartment 159
Rooms
3
Floor
14
sq.m.
59.8